Solo River Basin Sediment Removal & Channel Rehabilitation Project
The project focused on a 12-kilometer shallow section of the Solo River basin, where seasonal monsoon flooding had caused severe siltation. The accumulated sediment reduced river capacity and posed high flood risks to surrounding urban areas. The scope required dredging approximately 150,000 m³ of compacted mud, silt, fine sand, and small gravel to restore the natural waterway depth.


Customer Challenges
Shallow & Restricted Waterways: The water depth along the target river stretch was less than 1.5 meters with narrow bends, rendering conventional suction dredgers unusable.
Severe Clogging & Compacted Sediment: Dense mud mixed with river debris and small gravel frequently clogged standard electric submersible pumps, leading to constant downtime and labor costs.
Power Infrastructure Constraints: The job site lacked high-voltage power access, making electrical pump systems cost-prohibitive due to generator rental and fuel demands.
Abrasive Wear & High Maintenance: High concentrations of abrasive sand rapidly eroded standard pump components, threatening project timelines.
Our Solutions
Direct Excavator Integration: Deployed the Amoshydro® Hydraulic Dredging Pump mounted directly to the arm of an amphibious excavator. Powered by the host excavator’s auxiliary hydraulic system, the setup eliminated the need for external power generators or separate dredging barges.
High-Torque Mechanical Agitator: Fitted the pump with an integrated high-torque hydraulic agitator that pre-mixed compacted sediment and sand into a uniform slurry before entering the suction port, eliminating clogging issues.
High-Chrome Wear-Resistant Alloy: Manufactured all wet-end components (impeller, casing, and wear plate) using high-chromium alloy (Brinell hardness 600+), maximizing resistance against abrasive sand and gravel wear.
Long-Distance Slurry Transport: Connected an 8-inch flexible discharge line, enabling continuous slurry delivery over 500 meters into a designated containment pond.


Key Results & Benefits Delivered
90% Reduction in Downtime: Anti-clogging agitator design ensured uninterrupted 20-hour daily operation.
40% Cost Savings: Operating directly off excavator hydraulics drastically cut equipment mobilization and fuel expenses.
Early Delivery: The 150,000 m³ dredging objective was fulfilled two weeks ahead of schedule.
Watch this Amphibious Excavator-Mounted Hydraulic Dredging Pump Operation to see how an excavator-mounted hydraulic dredging pump breaks up and pumps heavy sediment in shallow waters