Palm Jebel Ali Coastal Protection Reef Construction (Sand Transfer)
Implementation of precise sand placement for the construction of a submerged offshore coastal protection reef. The scope required the accurate transfer of approximately 500,000 m³ of fine, abrasive sand from a nearby borrow area to specified reef coordinates. The project specified a placement tolerance of ±20cm relative to the target underwater elevations. Dredging utilized high-volume pumps operated from modified excavator barges working with GPS-guided placement systems.


Customer Challenges
Constructing an offshore submerged reef required large volumes of clean sand to be accurately placed at specific depths. Access for large hopper dredgers was limited due to water depth constraints and the high cost of mobilized large vessels for precise, small-scale material placement. The sand was very fine but highly abrasive.
Our Solutions
We provided a high-volume Amoshydro® Hydraulic Submersible Sand Transport Pump. The pump was integrated into a simple, floating barge-mounted excavator system. To ensure high production of clean sand, the hydraulic power unit was optimized for high flow. The pump utilized advanced abrasive-resistant alloys. Sand was pumped via a floating pipeline 400m to the reef construction site, where GPS-guided excavators managed precise underwater placement.


Key Results & Benefits Delivered
Precision Placement: Met stringent placement tolerances (±20cm), critical for reef stability, which was difficult for large vessels.
Production: Achieved sand transfer rates exceeding 950 m³/hour (dry solids).
Cost Efficiency: Project was delivered at 30% lower cost than using a dedicated trailing suction hopper dredger (TSHD) for the same volume.