High-Volume River Dredging in Indonesia

Located within a complex industrial excavation site in Indonesia, this project is centered on critical waterway maintenance and heavy slurry management. The working environment presents significant geographical challenges, characterized by uneven rocky terrain, soft marshy banks, and expansive settling ponds filled with dense, sediment-heavy water.

The primary objective of this operation is to efficiently clear accumulated silt, coarse sand, and abrasive debris from the site’s water bodies. Removing this dense sediment is essential to stabilize the surrounding banks, restore water capacity, and ensure the safe, uninterrupted continuation of broader site operations. Due to the inability of standard machinery to operate on the soft edges of the water, the project relies on specialized amphibious dredging methods to safely navigate the unstable terrain and execute continuous, high-volume extraction in this demanding environment.

Indonesia Amphibious Excavator Mounted Submersible Pump (2)
Excavator Mounted Desilting Pump (1)

Dredging operations in Indonesia frequently present demanding environmental obstacles. For this inland project, contractors faced a combination of deep, soft mud adjacent to rocky, uneven terrain and open water. Standard tracked excavators lack the necessary flotation and risk sinking into the soft banks, while conventional dredging methods struggle to break up the dense, rocky silt visible across the site. The client required an adaptable, heavy-duty solution that could integrate directly with their existing SANY excavator, providing both the stability to navigate the challenging landscape and the power to extract heavy, abrasive slurry.

To overcome these site-specific challenges, the excavator was upgraded with two critical components: our specialized pontoon-style River Undercarriage and the heavy-duty Amoshydro® HTU-T 150-50 Hydraulic Submersible Dredging Pump.

The massive pontoon undercarriage replaces standard tracks, providing the essential broad-stance flotation required to keep the SANY machine stable and elevated above the deep mud and water line. Paired with this is the HTU-T 150-50 pump, engineered with robust side agitators specifically designed to cut through and mobilize the coarse, rocky deposits found on the riverbanks.

Indonesia Amphibious Excavator Mounted Submersible Pump (3)
Indonesia Amphibious Excavator Mounted Submersible Pump (1)

Equipment is only as reliable as its setup, especially in unforgiving field environments. The installation was conducted directly on the rugged job site, with the local crew working hands-on to secure the hydraulic lines and mounting brackets to the SANY boom. The seamless integration demonstrates the high compatibility and straightforward plug-and-play nature of the HTU series, allowing the team to finalize the setup efficiently and stand proudly with the completed rig.

Once deployed, the upgraded SANY excavator immediately transformed the site’s operational capabilities:

Operational Reliability: Built for durability in extreme conditions, the rugged construction of the pump and undercarriage ensured continuous operation, maximizing uptime for the Indonesian contractor.

Unmatched Stability: The River Undercarriage allowed operators to maneuver confidently across the soft, unstable terrain right to the water’s edge without the risk of bogging down.

Aggressive Slurry Extraction: The HTU-T 150-50’s agitators effectively chewed through the heavy, rocky soil, maintaining a high-volume flow of abrasive slurry that standard pumps cannot handle.

Excavator Mounted Desilting Pump (3)

related products

size range/dimensions:
2" (50mm) thru 16" (400 mm)
Head:
15-65m
capacity:
Up to 10,000 GPM (2,275 m3/hr)
Material :
High-Chrome Alloy (27% Cr / A05)
get a quote >>

other cases

Indonesia Indonesia
The project focused on a 12-kilometer shallow section of the Solo River basin, where seasonal monsoon flooding had caused severe siltation. The accumulated sediment reduced river capacity and posed high flood risks to surrounding urban areas. The scope required dredging approximately 150,000 m³ of compacted mud, silt, fine sand, and small gravel to restore the natural waterway depth.
Indonesia Indonesia
Located within a complex industrial excavation site in Indonesia, this project is centered on critical waterway maintenance and heavy slurry management. The working environment presents significant geographical challenges, characterized by uneven rocky terrain, soft marshy banks, and expansive settling ponds filled with dense, sediment-heavy water.
United Arab Emirates (Dubai) United Arab Emirates (Dubai)
An active gold mining operation in the mineral-rich East Region of Cameroon required a massive overhaul of its tailing sand recovery process. The project focused on reclaiming legacy tailing ponds and dredging active alluvial sites to extract remaining gold deposits. The scope required a heavy-duty pumping system capable of transporting dense, abrasive sand, gravel, and mud mixtures over a distance of up to 2 kilometers to the central gold separation dredger, all within a rugged, off-grid environment.
Queensland, Australia Queensland, Australia
Ongoing reclamation of consolidated gold and copper tailings from an active tailings storage facility for hydraulic re-processing at the mine's main mill. The scope involved the precise reclamation of approximately 100,000 m³ of material per year. The project utilized a customized long-reach excavator operating on the TSF surface, fitted with the Amoshydro® pump to feed a re-pulping system at a consistent pulp density of 55% solids by weight.
Peru Peru
Implementation of Phase 1 of a major de-silting program to recover reservoir storage capacity. The scope focused on the removal of 400,000 m³ of ultra-fine glacial silt from critical operational zones, specifically near the powerhouse water intakes. The project utilized modular dredging units operated from custom barges in water depths ranging from 5 to 15 meters. Dredged material was pumped uphill via a specialized 600m pipeline to a designated upland settlement basin, requiring dynamic head management.
Singapore Singapore
Removal of approximately 250,000 m³ of consolidated, fine black marine silt from two critical ultra-large container vessel berths. The project required reaching a specified maintenance depth of -16.0 meters below chart datum. The scope included continuous 24/7 pumping operations over a 6-month period, delivering the high-density slurry to a disposal area via an 800m+ floating and submerged pipeline system with a target discharge density of 1.25 t/m³.