New Alamein City Coastal Fill & Land Reclamation Project
Excavation and hydraulic transport of 1,200,000 m³ of clean offshore seabed sand and silt mixtures to reclaim a 35-hectare coastal zone. This reclaimed land formed the foundation for a new luxury marina and waterfront promenade in the Mediterranean resort city.


Customer Challenges
The project required moving massive volumes of seabed solids over a long distance within a tight construction schedule. The material was a difficult mix of fine sand and silt that tended to compact and cause sedimentation in the long discharge pipeline. The offshore area was also subject to Mediterranean wave action, requiring a stable dredging platform.
Our Solutions
We deployed two high-capacity Amoshydro® Hydraulic Dredging Pumps mounted on a large, spud-stabilized cutter suction dredge. The pumps were configured in a series-booster arrangement to provide the exceptional pressure required to push the sandy slurry through a 3.5-kilometer overland discharge pipeline to the reclamation area.


Key Results & Benefits Delivered
High-Volume Capacity: The dual-pump series system moved an average of 6,000 m³ of material per day, keeping the massive reclamation project on schedule.
Long-Distance Pumping: Effectively transported the solids over 3.5 kilometers without requiring intermediate booster stations, simplifying overall site logistics.
Stable Operations: The spud-dredge platform provided stability against Mediterranean swells, allowing for continuous operation.