Coastal Infrastructure & Waterfront Development

Industry
Land Reclamation & Dewatering
Location
Egypt
Application
Coastal Infrastructure & Waterfront Development

Excavation and hydraulic transport of 1,200,000 m³ of clean offshore seabed sand and silt mixtures to reclaim a 35-hectare coastal zone. This reclaimed land formed the foundation for a new luxury marina and waterfront promenade in the Mediterranean resort city.

Sea Industry Wood Truck Cargo Forest Ground Lumber Deforestation Machinery, For Vehicle Tractor
Bg035

The project required moving massive volumes of seabed solids over a long distance within a tight construction schedule. The material was a difficult mix of fine sand and silt that tended to compact and cause sedimentation in the long discharge pipeline. The offshore area was also subject to Mediterranean wave action, requiring a stable dredging platform.

We deployed two high-capacity Amoshydro® Hydraulic Dredging Pumps mounted on a large, spud-stabilized cutter suction dredge. The pumps were configured in a series-booster arrangement to provide the exceptional pressure required to push the sandy slurry through a 3.5-kilometer overland discharge pipeline to the reclamation area.

Excavator Mounted Submersible Dredging Pump With Agitators
Hydraulic Abrasion Resistant Sand Sludge Pumps (3)

High-Volume Capacity: The dual-pump series system moved an average of 6,000 m³ of material per day, keeping the massive reclamation project on schedule.

Long-Distance Pumping: Effectively transported the solids over 3.5 kilometers without requiring intermediate booster stations, simplifying overall site logistics.

Stable Operations: The spud-dredge platform provided stability against Mediterranean swells, allowing for continuous operation.

related products

size range/dimensions:
2" (50mm) thru 16" (400 mm)
temperature range:
Standard Design: 104°F, Options to 176°F
capacity:
Up to 10,000 GPM (2,275 m3/hr)
get a quote >>

other cases

Indonesia Indonesia
The project focused on a 12-kilometer shallow section of the Solo River basin, where seasonal monsoon flooding had caused severe siltation. The accumulated sediment reduced river capacity and posed high flood risks to surrounding urban areas. The scope required dredging approximately 150,000 m³ of compacted mud, silt, fine sand, and small gravel to restore the natural waterway depth.
Indonesia Indonesia
Located within a complex industrial excavation site in Indonesia, this project is centered on critical waterway maintenance and heavy slurry management. The working environment presents significant geographical challenges, characterized by uneven rocky terrain, soft marshy banks, and expansive settling ponds filled with dense, sediment-heavy water.
United Arab Emirates (Dubai) United Arab Emirates (Dubai)
An active gold mining operation in the mineral-rich East Region of Cameroon required a massive overhaul of its tailing sand recovery process. The project focused on reclaiming legacy tailing ponds and dredging active alluvial sites to extract remaining gold deposits. The scope required a heavy-duty pumping system capable of transporting dense, abrasive sand, gravel, and mud mixtures over a distance of up to 2 kilometers to the central gold separation dredger, all within a rugged, off-grid environment.
Queensland, Australia Queensland, Australia
Ongoing reclamation of consolidated gold and copper tailings from an active tailings storage facility for hydraulic re-processing at the mine's main mill. The scope involved the precise reclamation of approximately 100,000 m³ of material per year. The project utilized a customized long-reach excavator operating on the TSF surface, fitted with the Amoshydro® pump to feed a re-pulping system at a consistent pulp density of 55% solids by weight.
Peru Peru
Implementation of Phase 1 of a major de-silting program to recover reservoir storage capacity. The scope focused on the removal of 400,000 m³ of ultra-fine glacial silt from critical operational zones, specifically near the powerhouse water intakes. The project utilized modular dredging units operated from custom barges in water depths ranging from 5 to 15 meters. Dredged material was pumped uphill via a specialized 600m pipeline to a designated upland settlement basin, requiring dynamic head management.
Singapore Singapore
Removal of approximately 250,000 m³ of consolidated, fine black marine silt from two critical ultra-large container vessel berths. The project required reaching a specified maintenance depth of -16.0 meters below chart datum. The scope included continuous 24/7 pumping operations over a 6-month period, delivering the high-density slurry to a disposal area via an 800m+ floating and submerged pipeline system with a target discharge density of 1.25 t/m³.