Narmada Main Canal Desilting and Rehabilitation
Implementation of desilting operations along a 50km segment of the Narmada Main Canal system to restore original water flow capacity. The scope required the precise removal of approximately 300,000 m³ of compacted silt and fine sand from the canal bed while the canal remained fully operational. Operations utilized long-reach bank-mounted excavators, pumping the slurry over 700m to upland disposal sites, with strict turbidity control targets of maintaining resuspended turbidity levels below 50 NTU.


Customer Challenges
The main irrigation canal system was severely silted, reducing water flow by over 25% and affecting downstream agricultural production. The canal water must flow during the dredging; it cannot be drained. The sediment was compacted silt and fine sand. Access for large machinery was restricted to narrow service roads.
Our Solutions
A precision, low-turbidity approach was required. We deployed three Amoshydro® Hydraulic Submersible Slurry Desilting Pumps optimized for long-distance, high-pressure slurry discharge. The pumps were operated from bank-mounted excavators using long-reach booms. To handle compacted sand and minimize resuspended turbidity (critical for maintaining water quality), the pumps featured high-torque hydraulic side cutters and a refined positive displacement agitator. Slurry was pumped 700m to a settlement area.


Key Results & Benefits Delivered
- Flow Restoration: Successfully restored 95% of original canal water flow capacity.
- Turbidity Control: Maintained average resuspended turbidity levels below 50 NTU, ensuring downstream water suitability for irrigation.
- Continuous Water Supply: Project was completed while the canal remained active, causing zero disruption to downstream farmers.